Road and Bridge Construction

Proposed 2025 County Project Schedule:

May 1 - June 23 (Completed)

Division 2 Road Construction

Twp Rd 484 between Rge Rd 102 and Rge Rd 103

1.0 miles

Back sloping and grade widening

June 23 - July 11 (Completed)

Division 3 Bridge Culvert (BF 78718)

Twp Rd 512 West of Rge Rd 80

Entire bridge culvert replacement

June 19 - July 22 (Completed)

Division 7 Bridge Culvert (BF 75589)

Twp Rd 532 West of Rge Rd 155

Entire bridge culvert replacement

June 23 - August 26 (Completed)

Division 3 Road Construction

Rge Rd 85 between Twp Rd 512 and Rge Rd 84A

1.2 miles

Back sloping and grade widening

July 28 - August 28 (Completed)

Division 5 Bridge Culvert (BF 01819)

Rge Rd 123 South of Twp Rd 512

Entire bridge culvert replacement

August 11 - September 15 (Completed)

Division 7 Bridge Culvert (BF 75604)

Rge Rd 145 South of Hwy 631

Entire bridge culvert replacement

August 13 - October 22 (Completed)

Bridge Closure - (BF 00931)

Range Road 142 North of Township Road 540

August 26 - October 15 (Completed)

Division 1 Road Construction

Intersection of Township Rd 490 and Range Rd 85

0.4 miles

Slough and intersection upgrades

September 22-October 9 (Completed)

Division 5 Road Closure

Township Rd 514 between Range Rd 135 and Range Rd 140

Pipeline Work

October 15 (Completed)

Rge. Rd. 91 between TWP. Rd. 492 and TWP. Rd. 494 is now closed and will tentatively reopen on Monday, October 20, 2025.

October 17 - TBD

TWP. Rd. 504 between RGE Rd. 133 to RGE. Rd. 135 is now closed and will tentatively reopen on Wednesday, October 29, 2025.

October 27 - TBD

Division 4 Bridge Repairs (BF 01865)

Twp Rd 532 from Rge Rd 142 to Rge. Rd. 143

Bridge maintenance and repairs

TBD

Division 1 Bridge Repairs (BF 74718)

Twp Rd 502 East of Rge Rd 85

Bridge maintenance and repairs